A26 dualling - Glarryford to A44 Drones Road


Construction scheme (current)
To dual about a third of the A26 between Ballymena and Ballymoney, which forms part of the main route north from Belfast via Antrim to Coleraine.
BAM/McCann consortium
Total Length
7.0km / 4.4 miles

Scheme proposed in RSTN TP, 2005

Public Information Day held 15-16 Nov 2006

Preferred route announced - 11 Aug 2008

Draft legal documents published - 20 Mar 2012
Public Exhibition - 26-27 Mar 2012
Public Inquiry took place from 5 Nov 2012

Scheme given finance and approved for construction 21 Oct 2013

Scheme put out to initial tender - 4 Dec 2013

Advance site works contract began - 27 Jan 2014

Award of contract to BAM/McCann consortium - 21 Oct 2014
Official contract start date - 19 Jan 2015

Contractor mobilisation works began on site - Early Feb 2015
Official sod-cutting ceremony - 26 Mar 2015

Construction began - 30 Mar 2015
To last 28 months, thus completion due - Aug 2017

(changed from "by 2018" as of Nov 2008, changed from "early 2010" as of Nov 2006)


£65m (as of Dec 2013)
(revised from £61m as of June 2012; revised from £50m-£70m as of April 2010; £52m as of August 2008; itself revised from £33.4m as of 2006; and that revised from £22.9m as of 2005)

See below.
See Also

General area map

Official web site for the scheme (Roads Service)

Leaflet, including basic design of the new road - PDF format
Part 1 and Part 2 of the detailed design - PDF format

A26 Ballymena to Glarryford on this site

Click here to jump straight down to updates for this scheme.

The A26 is the principal route north from Antrim to Coleraine, passing Ballymena and Ballymoney on the way. It is very busy, particularly at peak times and in the summer when holidaymakers go to the north coast. If the original motorway plans of the 1960s had taken place, this traffic would all be carried by the M2. However, the M2 was never completed and so the A26 carries the burden. The dualling of the section from Antrim to Ballymena was completed between 1989 and 2001. The section north of Ballymena, which according to Roads Service carries 18,000 vehicles per day, has been dualled as far as Glarryford (about 7km). This scheme will see the next 7km dualled as far as the A44 Drones Road junction where all the traffic for Ballycastle diverts. The map below shows the section in question in red. The red pins indicate the locations of grade separated junctions, while the blue pin is a ground level roundabout.

The route of the scheme, announced in August 2008, is essentially an online upgrade of the existing road, drifting offline only to bypass the Frosses Trees and to cross a river near Clogh Mills. The road will have three "compact" grade separated junctions (ie flyovers) which are, from south to north at:

  • B64 Springmount Road/Station Road (near Glarryford)
  • C61 Lisnasoo Road (just north of the Frosses Trees)
  • B93 Killagan Road / B94 Drumadoon Road (at Logan's Fashions)

Other than these locations, vehicles will NOT be permitted to turn right across the central reservation which will be entirely closed. There will be ten left-in/left-out T-junctions along the road to give access to properties and farms not accessible from the grade separated junctions. The upgrade will terminate at a new roundabout at the A26/A44 Drones Road junction which is currently a Y-junction for traffic heading to Ballycastle to diverge. The Frosses Trees will be preserved in the form of two laybys adjacent to the upgraded road. You can see a map of the proposed road in PDF format by clicking here. Please tell me if this link does not work, as Roads Service sometimes change links. The road will feature a shared foot/cycleway along its length. You can see a much more detailed design by clicking here and here.

The purpose of the scheme is to reduce traffic congestion by increasing the road's capacity/overtaking opportunities, and improving safety by reducing conflicting movements and eliminating head-on overtaking. Arup were commissioned in April 2006 to develop the project.

The Frosses Trees

The famous "Frosses Trees" section of the A26 is near Clogh Mills where beautiful mature trees were been planted down each side in 1839 creating a tunnel effect (see photo below). The trees are arranged in two groups - the larger, southern, one known as the "Big Frosses" and the smaller, northern one, known as the "Wee Frosses". Many local children try to hold their breath as they travel the full length of the trees! Although a number of trees have been felled recently due to their age, the public would not tolerate any attempt to remove this feature. The design of the road has therefore been carefully selected to preserve this remarkable feature in the form of two lay-bys so that drivers can still visit them. See photos below for a picture of the Frosses Trees.

Other Routes Considered

Roads Service considered five route options before settling on the Blue Route.

  1. The Orange Route involves largely widening 60% of the existing road with an offline route on the northern end to the west of the current road.
  2. The Green Route is to widen 80% of the existing road with 20% of the northern end offline to the west.
  3. The Blue Route is to widen the existing road in its entirity. This option was chosen.
  4. The Red Route is an almost entirely new alignment to the east of the current road.
  5. The Yellow Route is only entirely offline east of the current road at the south end and to the west at the north end.

Maps of these options are available here.


16 Sep 2015: In the month since the previous update a lot has happened on the scheme. At Glarryford, the earthworks for the approach embankments for the new flyover junction are now very advanced (pics 1, 2), and the huge scale of them visually dominates the area when driving through. There is still no sign of work on the bridge abutments themselves, but there is still plenty of time for that. Most of the heavy plant machinery has now been moved north to Lisnasoo Road (pics 4, 5), where the next major flyover junction is to be built, so presumably we are going to be seeing major earthworks there in the coming weeks. An accommodation road is being built to provide alternative access to property along the new road here. At the Frosses Trees (between Glarryford and Lisnasoo Road), which the new road will completely bypass (east of the "Big Frosses" and west of the "Wee Frosses"), the foundations of the new road are now very evident off to one side (pic 3). The two sets of Frosses Trees will be preserved in the form of laybys, as it was not possible to upgrade the road through them. The pictures below were all taken three days ago by Adrian Martin (thank you once again) and are arranged in order from south to north.

Pic 1: Taken from the B64 Station Road, this is the view north-east towards Glarryford Cross on 13 Sep 2015. The main A26 is now obscured by the embankment but it runs left-right in front of the small white house to the left of centre. This is the approach embankment to the future flyover. It looks to me as if the old Station Road has simply been buried in situ, which will be something interesting for future generations to dig up! Compare this to the photo taken at the same location a month ago in the previous update below. [Adrian Martin]

Pic 2: It is hard to believe that this is the view south along the A26 at what was, until recently, Glarryford Cross. Taken on 13 Sep 2015, the sign in the foreground is actually the "Give Way" sign sited at the point Station Road (which ran to the right) met the main northbound A26 (on which the photographer is standing!). You can see this sign before the recent works in Google Streetview, which will allow you to get your bearings. The curved embankment ahead is the future northbound onslip from the flyover which will eventually pass overhead just a few metres beyond the sign. [Adrian Martin]

Pic 3: Further north, this is the view northbound approaching the "Wee Frosses", ie the shorter of the two stretches of trees, on 13 Sep 2015. The new dual-carriageway will entirely bypass the Wee Frosses to the left here, and the foundations for this are already taking shape. This area is composed of soft peat which presumably had to be excavated or otherwise stabilised to be able to take the weight of the new road without subsiding. [Adrian Martin]

Pic 4: View north along the A26 at Lisnasoo Road on 13 Sep 2015. This is the site of the second flyover junction, and large amounts of earth moving equipment have been moved to this vicinity in the past week or two, so expect to see major work here soon. The flyover itself will be behind the photographer, but the wider new road will occupy the area in the left foreground when finished. The small roadway under construction on the left (under the striped poles) is an accommodation road which will eventually give access to fields and houses since most direct accesses onto the new road will be closed up for safety reasons. This accommodation road will join the main road network at Lisnasoo Road junction. [Adrian Martin]

Pic 5: At Lisnasoo Road a veritable army of heavy plant equipment sits waiting for use on 13 Sep 2015. [Adrian Martin]

19 Aug 2015: Four months since the previous update, and five months since the project began and we have more photos, thanks to Adrian Martin. These pictures are all taken at or near Glarryford Cross, a staggered crossroads at the very south end of the scheme. (This focus on Glarryford is not to imply that this is the only place where work is taking place, but because this is the part of the site Adrian visited - thank you!). Just to the south-west of Glarryford Cross is where the current A26 dual-carriageway from Ballymena ends. The two carriageways crossed over the Clogh river on two separate bridges, a 1960s one and a 19th century one (see previous update). All traffic has now been diverted onto the 19th century bridge, rather confusingly called Newbridge Bridge, and the 1960s Crankill Bridge has now been demolished. Work will presumably start soon on its replacement, a much wider bridge that will carry the entire new dual-carriageway. About half a km north-west of these bridges is Glarryford Cross itself, which was at the very end of the old dual-carriageway. Again, all traffic is now using the southbound carriageway here. It is to be replaced by a compact grade-separated junction with an overbridge. Unfortunately a loop of the Clogh river was in the way of the approach embankment for the bridge, so this has now been cut off, as shown in the photos below. I have included a map below in case it helps to illustrate what I'm trying to say here. Finally, earthworks have begun with at least one of the approach roads, Station Road, diverted to allow work on the embankment for the bridge to commence. Regular users of the route have noted that the past month has seen significant changes here. In July work was briefly disrupted when workers discovered armaments along the site of the scheme. The pictures below were all taken by Adrian Martin. The first two were taken on 26 July, and the rest on or near 15 August.

Map of the proposed layout at Glarryford Cross overlaid on a map of the current arrangement. The inconvenient loop of the Clogh River is shown by a blue line, and the cut through the loop marked in a thin black line. North is to the bottom right. Roads Service map from here.

Pic 1: The closed northbound carriageway of the A26 seen from Glarryford Cross on 26 July 2015 with B64 Station Road to the right. All traffic is using the southbound carriageway, which is not visible beyond the left of the machinery. The pile on the right appears to be pieces of broken-up road surface, perhaps from the demolished bridge? (see below). [Adrian Martin]

Pic 2: Excavation of the cut through the meander of the Clogh River underway but not yet completed on 26 July 2015. [Adrian Martin]

Pic 3: Now moving ahead to 15 August 2015, this is the view heading north-west from Ballymena about half a mile south of Glarryford Cross where all traffic has to switch over to the southbound carriageway. This is not merely to convenience the contractor - the bridge for the northbound carriageway is now gone, which is a good reason to avoid driving on it! [Adrian Martin]

Pic 4: View of the recently-demolished 1960s Crankill Bridge on 15 August 2015, which used to carry the northbound carriageway. This will be replaced by a wider, modern structure that will carry the entire road. Taken from the 19th century Newbridge Bridge which will remain in situ, but not in use as a through road, for historical reasons. The pipe-like structure is presumably there to accommodate services such as water or telephone lines that run along the road. [Adrian Martin]

Pic 5: The "cut" in the loop of the Clogh River complete and in use on 15 August 2015, with the original course of the river on the left now completely filled in. [Adrian Martin]

Pic 6: Switching onto the B64 Station Road, this is the view north-east towards Glarryford Cross on 15 August 2015. The road has been diverted, as the area to the right ahead is to become the site of the approach embankment for the future flyover. A lot of trees have been felled here; the site looks very different than it did a few months ago when the house on the hill ahead was barely visible from here. [Adrian Martin]

Pic 7: View north-west, towards Ballymoney, along what was the northbound carriageway of the A26, on 15 August 2015. All traffic is using the southbound carriageway on the right. This was the spot where the existing dual-carriageway finally ended and the single-carriageway to Ballymoney began. The wires with flags are to warn construction workers of the overhead cables. [Adrian Martin]

17 Apr 2015: Work got underway properly on 30th March, following the DRD Minister officially cutting the first sod on the scheme on 26 March. You can see photos from the ceremony on the FP McCann web site here (part of the BAM/McCann consortium who are building the road). The most obvious change from the point of view of drivers is that the last half mile or so of the existing dual-carriageway approaching Glarryford has been coned down to one lane, and a contra-flow put in, presumably because this part of the dual-carriageway is being modified as part of the works. This is shown in picture 1 below, shared by Adrian Martin (thank you). At Glarryford crossroads itself, earth moving equipment was evident on the day of Adrian's visit (picture 2). This will be the site of one of the future grade-separated junctions so is probably related to that. People who travel this road will know that northbound traffic uses the modern 1960s Crankill Bridge, while southbound traffic uses the original (late 19th century?) Newbridge Bridge. The plan is to widen replace Crankill Bridge to carry both carriageways of the upgraded road. Newbridge Bridge will then be closed to vehicles, but is to be preserved in-situ because it has historical significance (rather like old Shaw's Bridge in Belfast). With thanks also to Will Hughes for updates on progress.

View north along the last part of the existing dual-carriageway approaching Glarryford crossroads on 5 April 2015. Both carriageways have been reduce to one lane. Workers are creating a crossover on the right, presumably to facilitate a contra-flow. [Adrian Martin]

View north along the existing A26 at the Station Road (Glarryford) junction on 5 April 2015. This will be site of a new grade-separated junction, so expect to see major earthworks taking shape here in the coming months. [Adrian Martin]

25 Mar 2015: VMS signage on the site indicates that work proper will get underway on this scheme on Monday, 30th March. Someone "in the know" has told me that the preliminary work that has taken place up until now has included "cone penetration testing", which would be the contractor finding out more about the structure of the ground at various locations. With thanks to three different people who contacted me with the information about the VMS signage - much appreciated. We can look forward to seeing work progress. Completion is due around August 2017 based on a construction period of 28 months.

11 Mar 2015: According to a Question for Written Answer in the Assembly last week, the contractor did indeed begin moving material and equipment onto the site in February as reported below. However, construction work "proper" will not begin until April. With an estimated construction period of 28 months, this would now place completion in August 2017. The written answer also states that the contract formally began on 19 January 2015.

28 Feb 2015: Since the previous update there has been no further sign of work, so my declaration of work being underway in early February may have been premature! There was a Written Answer in the Assembly on this topic two weeks ago. It has emerged that "Following contract award, a dispute arose between the contractor and the Department. Despite this, BAM/McCann remained the most economically advantageous tenderer." This presumably refers to a disagreement that has now been resolved, but it may have delayed the commencement of scheme which we had previously expected to have begun by now. The Written Answer says that main construction works are now due to begin in "March/April 2015". Finally, it also confirms that the overall construction cost is still estimated to be £55m, so whatever the dispute was it doesn't seem to have affected the cost much. It will be good to see the project begin. Ten days ago the same contractor was awarded the construction contract for the A31 Magherafelt Bypass, which means they'll be working on both schemes simultaneously.

7 Feb 2015: Thanks to Gregor Kerr who was driving this way and spotted folks in high-vis jackets on site, and also reported that heavy machinery seemed to be arriving on site at Glarryford on Thursday. This sounds very much like the contractor (BAM McCann) gearing up to begin work, which is right on cue. Therefore I have moved this scheme from "future schemes" to "under construction". Hurrah! If the construction takes 28 months as suggested in October, then we should see completion by June 2017.

28 Jan 2015: Work on this scheme does not yet seem to have started. I contacted TransportNI a couple of weeks ago and they told me that work was actually scheduled to begin in February 2015 (not December as indicated in the press release in October), so we can expect it to begin any time. Over the past day or two TransportNI has moved the scheme to the "currently underway" list, but as I haven't ascertained whether or not the work is underway I will not move it just yet! Note that the DRD's web site is giving the cost as "£50-57m" which differs from what the DRD Minister said in December 2013 – that the total cost was "£65m". However, it's possible that the winning tender came in less than estimated which could account for this. We will presumably find out in due course.

31 Oct 2014: Great news for this scheme - the contractor BAM/McCann consortium was awarded the construction contract for this scheme on 21 October. This was accompanied by a press release on 29 October giving more details. The total value of the contract is given as £55m, which may not include not borne by the contractor, eg vesting of land, which is likely the reason why this is less than the overall estimated project cost of £65m. Work is likely to start "by the end of this year", which I would take to mean December, and will take 28 months, meaning completion is due in April 2017. Regular users of the road will start to see evidence of the contractor gearing up for work in the coming weeks. This will start with the establishment of site yards at appropriate points. Vegetation clearance and fencing off of the vested land has already been carried out during the year, so the first step will probably be the commencement of some of the earthworks. The DRD press release suggests that this web page will carry updates as work progresses.

Official DRD photo for the award of contract, showing the DRD Minister Danny Kennedy (centre) with Hugh McCann (seated, left) and William Diver (seated, right) from the appointed contactor BAM/McCann consortium.

25 Jul 2014: In the previous update I mentioned how preliminary site works would be taking place during 2014. People driving past will have noticed trees disappearing and new fences being erected. These fences separate the land vested by the DRD from the land still owned by private landowners, and are sometimes replaced by more permanent fences after the works are complete. The work also includes archaeological investigations. Doing this now reduces the changes of high-profile hold-ups, such as the well-publicised delays to the A32 Cherrymount Link in Enniskillen two years ago following the discovery of a significant crannog. The archaeological works have been taking place and a month ago Roads Service (or TransportNI as they are now called) revealed that they had found significant artefacts, including an early Christian souterrain. Here is an article in the Belfast Telegraph on the topic. The scheme is still out to tender, with the contractor currently expected to be appointed "in the autumn" with work presumably to start almost straight away.

20 Jan 2014: According to the DRD, and advance site works contract is to get underway on this scheme next week. This work is separate from the main construction contract which is still in the early part of the tendering process and won't go to ground until the autumn. The work involves three tasks which must take place before the main work begins. Firstly, they will be installing fences along all the land that has now been purchased from landowners along the route. This will make the boundary of the site clear to both the landowners and the eventual contractor. They almost invariably consist of wooden posts with wire stretched between them. Secondly, they will be conducting vegetation clearance, especially the removal of trees and hedgerows which are problematic to remove later in the year since there is legislation about disturbing nesting birds. This means less work for the eventual contractor who can immediately start into service diversions and earthworks. Thirdly, they will be stripping off topsoil, especially anywhere where archaeology is suspected to exist. DRD have a statutory duty to investigate any archaeology that is found or suspected to exist, and doing this work now reduces the chances of a later discovery delaying the scheme. I have not yet marked the scheme as "underway", as this advance site works contract is not the main contract and thus can't really count as the project beginning. As said above, we can expect this in the autumn.

8 Dec 2013: The scheme has now been put out to tender (on the DRD web site and on the EU tenders web page). This first tender is actually part one of a two part process, in which construction firms bid to be included on a selected list of firms that will be invited to submit a more detailed bid in the second round. This is done to prevent a situation where dozens and dozens of companies who have no chance of winning the work submit detailed bits and waste everyone's time. In this first round the companies have to demonstrate that they have the means, skill and have realistic expectations on what is involved to complete the work. Construction companies have until 28 January 2014 to submit their bids for inclusion. After that the second part of the tender process - the more detailed bidding - will be advertised. The selection of a contractor typically takes about nine months from now, so we're likely to see the winner appointed in autumn 2014 with work likely to begin almost straight away. This is good news for the construction sector as well as users of this road. Amended 9 Dec: The DRD Minister, in a Question for Written Answer in the Assembly, has confirmed that the current estimated cost of the scheme is £65m.

4 Dec 2013: Two days ago Roads Service finally published the outcome of the Public Inquiry and their response to it, known as the Departmental Statement. All the documents can be accessed here. While quite a few objections were made to the scheme, the Inspector made only minor recommendations which were all accepted in substance by Roads Service. These generally related to the impact on individual landowners near the scheme, and would be important to them, but do not have a significant impact on the scheme which will proceed more or less as planned. The construction tender is due to be released this month. It normally takes about 9 month from publication of a tender to construction work commencing, which is in keeping with Roads Service's own reference to work beginning in "late 2014". (While everything has been done above board and within the rules, I do think it was slightly bad form for the DRD Minister to have announced that the scheme would proceed prior to the public inquiry report being published. While it wouldn't have made any material difference in this case, the DRD needs to avoid giving the impression that public inquiries are mere "rubber stamp" exercises.) The inspector's report alludes to a plan by Logan's (a large retail operation on the route to be upgraded) to build a park-and-share facility on their property in apparent competition with Roads Service's planned similar facility which would be located nearby on the other side of the A26. The report was written some months ago, however, so the situation has probably moved on since then.

30 Oct 2013: Roads Service have now confirmed that my predictions in the last update were pretty close! Subject to the outcome of the public inquiry, construction will begin in "late 2014" and will last approximately 24 months. This means that we will see the road completed late 2016, three years from now. DRD have also stated that the public inquiry report and their response to it (the Departmental Statement) will be published "in the coming weeks". Finally Arup, the company designing the road for Roads Service, have put up a fabulous simulation of a journey northbound along the finished road on YouTube. Well worth a look, and enough to whet the appetite of anyone who endures this road regularly. If you want to see more detailed plans of the proposed road, click here.

21 Oct 2013: In the previous update (see below) I commented that I would be surprised if this scheme managed to proceed to construction ahead of the desperately-needed A6 Randalstown to Castledawson scheme. Well today I am surprised, because that is exactly what has happened. Today in the Assembly funding was announced that funding was being given to commence construction of this scheme "in 2014/15", ie it would begin any time from April 2014 to April 2015, so between 6 and 18 months from now. It seems slightly odd to have announced that a scheme is going to proceed before the outcome of the public inquiry has even been published, but this suggests that the inquiry inspector has recommended that the scheme proceed. I would anticipate that the public inquiry report and DRD's response (the "Departmental Statement") will be published in the near future. After that the scheme will probably proceed rapidly to procurement, a process which typically takes around 9 months, while the Vesting Order (to acquire the land) will also proceed. So in a best-case scenario we could be looking at work commencing in the autumn of 2014. No timescale has yet been given, but I would expect that construction of a scheme like this would probably take roughly two years, perhaps a bit more. I have also written a piece weighing up the decision to proceed with this scheme against the A6 over on my blog.

16 Sep 2013: There is still no sign of the publication of the report into the Public Inquiry that took place in November 2012 - DRD have now had the report in their possession for about 4 months. This is not an unusual length of time by any means, but I would like to think that we will see it, and their response (the "Departmental Statement"), published in the not-too-distant future. There are hints of other movements behind the scenes. In the last update I suggested that this scheme might benefit from the delay to the A5 dualling scheme. In a Written Answer published today, the DRD Minister certainly seems to be of this mind. He said "I have heavily promoted this scheme in the 2014/15 Capital Budget Exercise, and will continue to do so in the forthcoming October Monitoring Round, with a view to securing the funds to allow construction to commence in 2014/15." The DRD don't get money to spend on whatever major construction schemes they want. Rather, they have to ask for money for individual construction projects, and these compete on merit with bids from other Departments in the NI Executive, like Education and Health. The 2013/14 budget is already set (the A31 Magherafelt Bypass being one of the beneficiaries) so the 2014/15 budget round is the next available tranche of money. The DRD Minister seems to see this scheme as his priority for this funding round. He also details some of his apparent struggles with the Finance Minister in this way: "After initially declining the meeting [about funding the A26 scheme], I am happy to report that the Finance Minister has now recognised the importance of an early discussion on this issue, he has agreed to a meeting and we are due to meet in the near future." The DRD Minister had been specifically asked about the A26 scheme in this Written Answer, so he did not comment in this level of detail on other proposed road schemes. However, and not to diminish the advantages of this scheme, I would be surprised if it managed to proceed to construction ahead of the desperately-needed A6 Randalstown to Castledawson scheme.

27 May 2013: In the last update I noted that the Inspector at November's Public Inquiry was to have submitted her report to the DRD early in 2013, and according to this press release this now seems to have happened. The next stage will be the DRD's response, which will take the form of a Departmental Statement, which will take a few months to analyse and draft. Both it and the Inspector's report will then be published at once. It is just as well that the legal process is progressing, as this scheme seems to be one of those that *may* benefit from the delay in the A5 scheme. In the Assembly last week, the "Roads" Minister said "The situation is such that we now have to look at other potential schemes that can be brought forward. I have indicated that I am doing that in conjunction with Executive colleagues, principally the Finance Minister, and we will continue to do that. The schemes that are most procurement-ready include the A26 Glarryford scheme,... the A6 [Randalstown to Castledawson] scheme, the Magherafelt bypass and the A55 [Outer Ring widening at Knock] scheme in Belfast." There is, of course, no guarantee that this scheme will actually get the go-ahead, and of all those listed it is the furthest from being able to go to ground, but at least it's being considered.

11 Feb 2013: The minutes of a Roads Service meeting held in December, but only just published indicate that the Inspector at November's Public Inquiry will submit her report to the DRD "early in 2013". The DRD will have to take time to consider this, and will then publish both the report and their response (the "Departmental Statement"), presumably in a few months' time.

12 Dec 2012: The minutes of a Roads Service meeting held in June, but only just published, confirm that the estimated cost of this scheme has now been pinned down at £61m (as opposed to the range £50m-£70m). The Public Inquiry happened in November as planned. I would not expect to hear more on this for at least a year. The Inspector has to write her report, and then the DRD has to study it and respond.

8 Sep 2012: The DRD have announced that the Public Inquiry will begin at 10am on 5 November 2012, at the Tullyglass Hotel, Galgorm Road, Ballymena, BT42 1HJ. The Inspector will be Ms Eileen Brady. I would urge everyone with an interest in the scheme to turn up, as this is a crucial opportunity to have your concerns heard. The recent A5 public inquiry resulted in dozens and dozens of tweaks to address the concerns of landowners.

24 Jun 2012: As expected, the DRD Minister has announced that a Public Inquiry will be held into this scheme. It has only attracted 20 objections during the consultation period that ended in May 2012, but nevertheless Roads Service feel it appropriate to convene an Inquiry. It will probably be held in early November. There is currently no financial commitment to actually build the scheme, but it is important to keep progressing the scheme so that it is 'good to go' if and when money becomes available.

20 Mar 2012: The draft legal documents have just been published, a good bit later than anticipated last summer (see previous update). This includes a summary of the Environmental Statement (a document that has to be created to set out the pros and cons of the scheme); the draft Trunk Road Order (required to permit Roads Service to construct a new trunk road); the draft Vesting Order (which allows Roads Service to compel landowners to sell the land required); and a draft Stopping-Up Order (which allows Roads Service to compel some landowners to stop using direct accesses onto the A26). The first of these documents contains a map of the road as currently proposed. A public exhibition setting out the current position will be held at the Tullyglass House Hotel (178 Galgorm Road, Ballymena, Co Antrim BT42 1HJ) from 2pm to 9pm on 27 and 28 March 2012. I would urge all those with any interest in the scheme to turn up and talk to the Roads Service representatives. Any formal comments must be received by 11 May 2012. Comparing the preferred route map from 2008 with the map published now, the main change is to the design of the Killagan Road/Drumadoon Road compact grade separated junction (known to most people as the location of Logan's Fashions), where it seems more use will be made of the existing road network than originally planned. Presumably there will be a Public Inquiry: at this stage, a date in the autumn seems plausible, although nothing has been said officially. Note that there is currently no budget allocation to build this scheme - but it is being progressed through all these design and legal processes to that it is 'good to go' if and when money becomes available at a future date.

4 Jul 2011: The Minister has now said that the draft legal documents required to build the road will be published "later this year", and that a Public Inquiry will likely be held in Spring 2012. This is the first official indication that a Public Inquiry is expected within the next year, although it was mooted unofficially late last year (see previous update).

30 Dec 2010: In response to a written request for an update on this scheme, the Regional Development Minister gave an update on progress. He said that "it is planned to publish the Draft Orders early in 2011/12" (a milestone previously given as "mid 2011"). Construction is still far off, with the Minister saying only that subject to finance it "could" commence before 2018. I have been in indirect contact with a landowner affected by the scheme who tells me that he was contacted in mid November to say that the scheme is progessing as planned with the draft orders due to be processed by "late spring or early summer". He was told that while negotiations have gone well with most landowners, a few remain unhappy. A public inquiry was mooted for 2012.

2 May 2010: Roads Service have updated the costs on their web site, with the cost of the scheme being revised up from £52m to the range £50m-£70m. There is no change to the timescale.

22 Feb 2010: In a written answer in the Assembly, the Regional Development Minister has said that although this scheme is in the final stages of the assessment process, the next milestone (publication of legal documents) has been pushed back to "mid 2011", more than a year later than he stated in March 2009 (see below). Although this is a substantial delay, it will probably make no material difference to road users since construction has always been anticipated to be towards 2018 anyway.

18 Mar 2009: In a written answer in the Assembly, the Regional Development Minister has said the Enviromental Statement and draft orders (such as land aquisition) will be published during the 2009/10 financial year, ie by April 2010. He also confirmed that construction is not anticpated until the "latter part" of the investment period, ie in the 5-10 year timeframe.

2 Feb 2009: Roads Service released a leaflet about the scheme in November 2008. It summarises the scheme in its current form, including a map of the current design. It notes that "The ‘Preferred Route’ is now being developed which involves undertaking statutory procedures for environment,
planning and land acquisition and will lead to the publication of mandatory Draft Orders and an Environmental Statement. The ‘Investment Delivery Plan for Roads’ estimates that this scheme will be delivered within the period 2013 to 2018.
" It could thus be quite a few years before work commences.

11 Aug 2008: The preferred route has been announced - the entirely online Blue Route. The scheme also features three compact grade separated junctions which will lead to major safety improvements, and probably accounts for the fact that the price has risen from £33m in 2006 to £52m today. See above for more details.

24 Apr 2008: According to an Assembly written answer, the Department of Regional Development expects to announce the preferred route "around mid 2008". The process to decide between the five route options is still ongoing.

July 2006: The cost of £22.9m publicised in 2005 had increased to £33m by the time this public consultation was released in July 2006.


The beautiful "Frosses Trees" section of the A26 Frosses Road near Clogh Mills where trees are lined close along each side. Taken looking north in late August 2006. This stretch will be preserved as a lay-by. [Photo by Aubrey Dale]