|
|
Status
|
Construction scheme
(ongoing - 1 complete; 1 ongoing; 4 still
to do) |
|
Where
|
To
provide a number of individual
improvements to the A32 to improve access
to the new regional hospital in
Enniskillen. |
|
Total
Length
|
Series of individual
schemes - total length unknown |
|
Dates
|
Scheme first proposed -
July 2006
Scheme given go-ahead -
April 2008
See table below for
progress on individual elements
All schemes to proceed
by 2015 (as of Nov 2008)
|
|
Cost
|
£10m from the Dept
of Regional Development (as of 2008) plus
£5m from the Dept
of Health, Social Services and Public
Safety (as of 2009)
|
|
Photos
|
See below. |
|
See
Also
|
General
area map
|
The A32 is the principle route between Omagh and
Enniskillen and passes through the towns of
Dromore and Irvinestown. Now that there is a plan
to replace the acute functions of Omagh's Tyrone
County Hospital and Enniskillen's Erne Hospital
with a new hospital to the north of Enniskillen,
the government has planned a series of six
improvement schemes for the A32. These take the
form of realignments in some places, and 2+1
overtaking opportunities at others. The work is
taking place over a period of years. As of
December 2010 only one scheme is completed.
The upgrades consist of
the following (colours indicate progress):
| Scheme Name |
Work |
Location |
Progress
(as of Jul 2011) |
| Mullaghbane |
Realignment and widening over 0.7km |
Between Omagh and Dromore |
Carried out
between Jan 2009 and mid 2009 |
| Shannaragh |
2.2km part off-line realignment and part
online widening £7m |
Between Omagh and Dromore |
Currently
out to tender - work to begin December 2011
|
| Esker Bog / Drumskinny |
0.9km partial off-line realignment and
online widening £1.8m |
Between Dromore and Irvinestown |
Main
contract began Sep 2011.
(Advanced site works took place early 2010.)
Completion due by Mar 2012 (as of Sep 2011).
|
| Cornamuck |
1.4km off-line realignment £5.1m |
Between Dromore and Irvinestown |
Preferred
option to be announced "late 2011" (as of
Mar 2011). |
| New Park |
Off-line realignment |
Between Dromore and Irvinestown |
Unknown |
| Kilgortnaleague |
Off-line realignment and widening |
Between Irvinestown and Enniskillen |
Design work
underway |
The map below shows the
location of all but the first of these schemes
(Sidaire is now cancelled).

Photos
These are
all links to Google Streetview.
Updates
21 Sep 2011: The contract to carry out the Drumskinny
scheme was awarded
to Fox
Building & Engineering Ltd on
31st August, and a press
release was issued today confirming that
work is commencing. The same press release
confirmed that the total cost of the
Drumskinny scheme is now £1.8m, of which
the construction contract represents
£1m. The scheme will see almost 1 km of
the A32 realigned and straightened to improve
road safety. The completion date is given as
"March 2012", ie around 6 months' duration.
4 Jul 2011: The Minister has
given another update on this scheme via a Written
Answer in the Assembly. Drumskinny
is now due to get underway in September this year,
while Shannaragh is unchanged
with commencement still due in December. Cornamuck
is still a "priority" but the implication is that
there is not currently enough money to built it.
5 Jun 2011: The Drumskinny
scheme is currently out
to tender with a closing date of 16th June,
while the Shannaragh scheme was
out to tender during May. In a press
release, Roads Service confirm that work on
Shannaragh is due to begin in December this year
with completion "in 2012", while Drumskinny will
be completed "before the end of the current
financial year", which presumably means by April
2012. The tender document states that the work
will begin in "late August". Last month a serious
road accident occured at Shannaragh, at one
of the bad bends due to be removed by the scheme
there. While we do not know whether the road
alignment was a factor in this accident, it does
nevertheless highlight the value of upgrading the
A32.
25 Apr 2011: Due to the
deteriorating financial climate, there is
uncertainty over when the five remaining elements
of this scheme will be constructed. In a Question
for Written Answer last month, the Minister
said draft orders for the Shannaragh
scheme (the most imminent one) have now been
published. He also said that the "preferred
option" for Cornamuck (ie the
design Roads Service would like to build) will be
published "later this year". However, the Minister
could not give any firm committment to progress
with any of the schemes within a specific
timeframe. The design documents for Shannaragh are
on the DRD web site, but they don't seem to be
listed anywhere. You can find them by going to this
page and typing "Shannaragh" into the search
box. Meanwhile, the tender
for construction of the Shannaragh scheme was
advertised on 12th April and will close on 25th
May. This is earlier than expected, based on the
information we had in December (see below). The
Roads Service web site is
also saying that the Drumskinny scheme may
go to tender in May 2011.
7 Mar 2011: Roads Service have
provided some more information on the progress on
these schemes via a Question
for Written Answer. It confirms what we
already knew about the progress and gives new cost
estimates - Shannaragh is now £7m (down from
£8m in December), Cornamuck is £5.1m,
and Drumskinny/Esker Bog is £1.4m. This
press release issued on Friday suggests that
some new money has been made available which may
help some or all of these schemes to progress.
30 Dec 2010:
Some clarity at last on the various schemes (see
previous update) has come by scouring council
reports from earlier in the year. Part of what I
have found is a more up-to-date map by Roads
Service showing the various schemes. I have
included this map above. An update on each scheme
is given below based on the Fermanagh
and Omagh
council reports from Spring 2010 as well as this
more recent press release on the subject. On
the basis of this new information I have
re-written the text above to reflect the current
position.
- The Mullaghbane scheme no
longer appears in Roads Service documents,
presumably because it was completed in 2009. See
here
for contract details.
- On the Shannaragh scheme,
the legal orders and environmental statement are
due to be published "in the coming weeks". The
contract is scheduled to be awarded "late in the
2011/12 financial year", ie early 2012. This
scheme alone is estimated
to cost almost £8m.
- It seems that the Drumskinny
scheme is actually an extension of the Esker
Bog scheme, so they are being treated
as a single scheme. Advanced site works took
place early in 2010 with the main contract due
to be released in March 2011, according to the Roads
Service web site.
- There is no new information on the Cornamuck
or New Park schemes.
- The Sidaire scheme which was
to have been between Enniskillen and Irvinestown
has now been cancelled "due to escalating
costs associated primarily with very poor
ground conditions and the necessity to acquire
adjoining land and property".
- Design work is underway on the Kilgortnaleague
scheme.
5 June 2010: According to this
press release, work on the Shannaragh
scheme is now expected to commence "in 2012",
which is a year later than anticipated in
November. Bizzarely, the press release also says
that the Mullaghbane scheme "is
nearing completion" despite the fact that a press
release issued
over a year ago claims the same thing!
Strange time warps on the A32... So far only one
of these eight associated schemes has been carried
out. This
press release notes that design work is
being carried out on the Kilgortnaleague
scheme at the Enniskillen end. The Sidaire
scheme is still on the Roads Service "future
tenders" list (release date Dec 2010), but the Esker
Bog scheme has inexplicably now
disappeared from the list. However, a new scheme
called "Drumskinny" has
now appeared (with a release planned for Sep
2010). This may be the same thing, or it may be a
nearby scheme previously referred to as Cornamuck.
Who knows? It is not helpful to the public if
Roads Service are changing the names of schemes
half way through the planning process!
23 January 2010: The Esker
Bog and Sidaire
schemes have appeared on Roads Service's "future
tenders" list. The tender for the Esker Bog scheme
is due to be released in August 2010, while the
Sidaire one is due to be released in December
2010.
22 November 2009: This
press release from last week outlines the
current position on this scheme. The Esker
Bog scheme will apparently commence
"this financial year" subject to land acquision.
This presumably means by April 2010. The Sidaire
and Shannaragh schemes are
expected to commence in "early 2011" subject to
land acquisition and available funding. There are
no updates on the remaining four schemes.
7 June 2009: According to this
press release from about 3 weeks ago, the
scheme at Mullaghbane was nearly
completed while the scheme at Sidaire
may proceed "later this year if land acquisition
is successful". A public exhibition on the Shannaragh
scheme took place on 28 May 2009. The current
position, therefore, is that of the 8 schemes
planned for the A32, one is completed with seven
still to proceed.
11 Apr 2009: According to latest
information, the scheme at Mullaghbane
is actually underway now, with completion due in
May 2009. Work apparently began there in late
January and involves both carraigeway widening and
realignment over a distance of 0.7km. The
contractor is James Balfour & Sons Ltd. The
same information states that the scheme at Sidaire
is due to get underway next, likely by April 2010
(subject to acquisition of land) at a cost of
around £800,000. Information
on the Roads Service web site, meanwhile, suggests
that the tender for the Esker Bog
scheme will be released in Spring 2010. This
suggests construction *might* happen in 2011. The
remaining schemes are described as "a rolling
programme" which we believe are to be completed by
2015.
2 Mar 2009: The Regional
Development Minister answered a question in
Stormont on the timescale of these improvements.
In his
reply, the Minister confirmed that the
schemes would proceed separately, with only two of
them (at Esker Bog and Sidare) being planned to
open before the new hospital in Enniskillen opens
(currently planned for 2012). The reply also
mentions four of the other schemes which he says
will open after the hospital. The reply makes no
mention of the schemes at Drumbulcan and
Mullaghbane. It thus seems as if these
improvements will be provided over a period of
several years, rather than all at once in a single
contract. The reply also confirms that the DRD is
contributing £10m, and the Department of
Health £5m "to facilitate blue light
services on this stretch of road".
2 Feb 2009:
Over the past few months this scheme (or series of
schemes) has been moved into the preparation pool,
meaning that construction is anticipated within
the next five years. In November 2008 a
leaflet was issued about these proposals,
the wording of which suggests that the various
elements will be implemented separately, and that
some will involve building short stretches of road
offline. The leaflet gives the rationale for the
project as being to "reduce journey times,
provide a safer route and improve journeys for
Accident & Emergency services".
|