Northern Ireland Motorways:

Sections and Opening Dates

 

This table gives the opening dates of all motorway sections built in Northern Ireland. The cost, where known, is given along with the 2005 equivalent in brackets (calculated via www.measuringworth.com). Some adjacent sections that opened on the same date are listed separately if they were built under separate contracts.

Road Section Length Cost (2005 equiv) Date Opened
M1

Junctions 1 to 2

(Donegall Rd to Stockman's Lane)

2.1km £1.9m (£27.2m) 10 Jul 1962
M1

Junctions 2 to 6 (Stockman's Lane

to Lisburn Saintfield Rd)

8.8km £2.5m (£35.7m) 10 Jul 1962
M1 Junctions 6 to 7 (Lisburn Saintfield Road to Sprucefield) 2.9km £1.5m (£21.0m) 15 Dec 1963
M1

Junctions 12 to 13

(Birches to Verner's Corner)

7.2km £1.8m (£24.4m) 1 Dec 1964
M1

Junctions 7 to 9

(Sprucefield to Moira)

10.9km £3.4m (£44.1m) 6 Dec 1965
M1

Junctions 9 to 10

(Moira to Lurgan)

9.6km £3.5m (£43.6m) 28 Feb 1966
M2 Junctions 2 to 4
(Greencastle to Sandyknowes)
5.6km

£4.1m estimate

(£51.1m)

24 Oct 1966
A8(M) Sandyknowes to Corr's Corner 1.6km £2.3m (£28.7m) 24 Oct 1966
M1

Junctions 10 to 11

(Lurgan to Ballynacor)

3.2km

£1.8m estimate

(£21.9m)

27 Nov 1967
M12 Spur from Ballynacor 3.7km £2.0m (£24.3m) 27 Nov 1967
M1

Junctions 13 to 15

(Verner's Corner to Dungannon)

7.8km £4.9m (£59.6m) 23 Dec 1967
M1

Junctions 11 to 12

(Ballynacor to Birches)

8.8km £8.3m (£96.4m) 29 Jan 1968
M2

Junctions 10 to 12

(Ballymena bypass)

7.2km £5.0m (£55.1m) 26 Apr 1969
M2

Junction 5 to M22 junction 1

(Templepatrick to Dunsilly)

10.4km £4.1m (£38.8m) 26 Feb 1971
M22

Junctions 1 to 2

(Dunsilly to Ballygrooby)

4.5km £1.9m (£18.0m) 16 Aug 1971
M22

Junctions 2 to 3

(Ballygrooby to Artresnahan)

2.2km £1.2m (£9.7m) 30 Jan 1973
M2

Junctions 1A to 2  (Whitla Street / York Street to Greencastle)

4.0km £7.5m (£60.7m) 22 May 1973
M2

Junctions 4 to 5

(Sandyknowes to Templepatrick)

9.4km £6.2m (£34.8m) 4 Sep 1975
M5 M2 junction 2 to Hazelbank 2.3km £4.4m (£12.6m) 12 Sep 1980
M1

Junction 3 added

(Black's Road, east-facing only)

1.0km £2.3m (£4.1m) Dec 1988
M12

Western sliproads to M1 at junction 11

(Ballynacor)

1.4km £1.7m (£2.5m) Jan 1991
M2

Junction 7 added

(Crosskennan, offslips only)

1.4km £0.4m (£0.6m) 1 Oct 1993
M3 Junctions 1A to 1 (Middlepath Street) 1.3km £26.4m (£34.0m) 22 Jan 1995
M3 Junction 1 (Middlepath Street) to Sydenham Bypass 1.1km £6.2m (£7.3m) May 1998
M1 Junction 8 added (Blaris) and Junction 7 (Sprucefield) west facing sliproads removed

1.5km

excl. A101

£8m (£8.5m) privately funded 13 Oct 2003
M1

Widening to 3 lanes junctions 2 to 3

(Black's Road to Stockman's Lane)

2.1km £4.8m (£4.9m) 10 Aug 2004

Source: " The Northern Ireland Motorway Achievement", Roads Service and Motorway Archive Trust, 2002, ISBN: 0-9543056-6-3

Total expenditure on motorways in each four year period (2002 equivalent):

Period

Expenditure

(2005 prices)

Total kilometres constructed
1962 - 1965 £152.4m 31.9km
1966 - 1969 £380.7m 47.5km
1970 - 1973 £127.2m 21.1km
1974 - 1977 £34.8m 9.4km
1978 - 1981* £12.6m 2.3km
1982 - 1985* £0m 0km
1986 - 1989 £4.1m 1.0km
1990 - 1993 £3.1m 2.8km
1994 - 1997 £34.0m 1.3km
1998 - 2001 £7.3m 1.1km
2002 - 2005 £13.4m 3.6km

*These periods also saw the construction of the expensive A12 Westlink, not listed here.