Status |
Construction scheme (current) |
Where |
To smooth out two bad curves on the A4 at Annaghilla and A5 at Tullyvar, both near Ballygawley. |
Total Length |
3.8 km / 2.4 miles (at Annaghilla)
3.1 km / 1.9 miles (at Tullyvar) |
Dates |
Scheme announced January 2004
Route announced November 2004
Funding announced March 2005
Public inquiries held March 2006
Site clearance work began mid Nov 2007
Construction officially began 13 Feb 2008.
Completion due by Dec 2010 (as of Feb 2008). |
Cost |
c£18m (40% for Tullyvar, 60% for Annaghilla) - see important note on costs.
Funded through public/private partnership. |
Photos |
None as yet - please contact me if you have any to contribute. |
See Also |
General area plan (Annaghilla on left, Tullyvar on right)
Annaghilla map (from Roads Service)
Tullyvar map (from Roads Service)
A4 dualling - Dungannon to Ballygawley on this site
Please contact me if these links are broken. |
These two schemes are grouped together because they are close geographically, are funded together and are to be constructed at the same time. According to the DRD press release the scheme will see 3.8km of the A4 route between Ballygawley and Augher including a section of 2+1 lanes for overtaking opportunities in the eastbound direction. It will also see 3.1km of the A5 route straightened at a hill section between Ballygawley and Aughnacloy with climbing lanes at either side. See the links above for maps of the route.
Both will see twisty sections of the A4 and A5 straightened. This will increase average speeds, improve safety and increase overtaking opportunities. They will improve the A4 Fermanagh<>Belfast and A5 Dublin<>Derry routes. The funding is from the "PPP Package 2" announced in March 2005. This is the second of two major private sector investments in Northern Ireland's road system and will also see the A4 dualled from the end of the M1 motorway at Dungannon to Ballygawley (see link above).
Design
The Annaghilla section on the A4 between Augher and Ballygawley carried 7500 vehicles per day in 2004. The new road will run from 3.8km from its junction with Annaloughan Road to its junction with Ballynanny Road. A bend to the west of Annaloughan Road will also be removed. The road will feature staggered cross-roads at Annaloughan Road, Sess Road and Ballynanny Road. The latter two are the two tie-ins with the existing A4. A bridge will carry the Ballynasaggart Road over the new road with no access. The road will feature two lanes eastbound (as an overtaking opportunity) and one lane westbound. See Annaghilla map.
The Tullyvar section on the A5 between Ballygawley and Aughnacloy carried 5800 vehicles per day in 2004. The new road will run for 2.7km from its junction with Tullywinny Road and its junction with Lisginny Road. The road will climb up and over Tullyvar Hill and will feature climbing lanes in both directions on this stretch. Staggered cross-roads will be provided at Lisginny Road/Aghaloo Road and
with the existing A4 where it crosses the line of the new road mid way along the stretch. See Tullyvar map.
Note on Costs
In mid 2005 the combined cost for the main A4 dualling scheme and the upgrades of A4 at Annaghilla and the A5 at Tullyvar was given as £117.7m (£102m for the A4, £15.7m for Annaghilla/Tullyvar). However by the time the scheme began in February 2008, the combined cost was given as £134. The cost of £18m stated above is an estimate which assumes that the proportions of the costs remain the same. This may not be accurate so this figure should be taken as approximate.
Progress
13 Feb 2008: The first sod on the A4 dualling scheme, which includes the Annaghilla/Tullyvar upgrades, was cut today with completion due in December 2010. It's not clear if work here will begin immediately or indeed if it will end before December 2010. The cost also seems to have risen slightly, to approximately £18m.
22 Nov 2007: According to the Roads Service "roadworks" page, advance site clearance work began at Tullyvar on 12 Nov 2007, and at Annaghilla on 19 November, both to last about 3 weeks. It is unknown if the planned dualling scheme on the A5 announced a couple of weeks ago has affected plans for the Tullyvar part of this scheme.
13 Nov 2007: According to a Written Answer on this page from the Minister for Regional Development, commencement on this project has been pushed back to "early 2008" from "late 2007". This coincides with the start of the main A4 dualling scheme and the likely explanation is that the two are due to be taken forward as part of the same contract.
August 2006: It now seems likely that although they were planned before the A4 dualling scheme, they will be constructed as part of that contract and at the same time. |